This Historic Iron Truss Bridge was removed from Milton Township Road 957 and donated for use here on the Wellston Bike Path.
This project was finished in December 2003.
County Rd. 4 - paved with ODOT #448 asphalt by county highway forces,
completed August 2004
County Rd. 8 - paved by county forces with cold mix asphalt paving material (produced by county forces),
completed August 2004
County Rd. 66 - paved with ODOT #448 asphalt by county highway forces -
completed July 2004
County Rd. 17, Structure 00.06 - new galvanized steel bridge and precast concrete block abutments,
completed August 2004
County Rd. 14, Structure 00.32 - new galvanized steel bridge on existing concrete abutments, completed August 2004